Every permitted disposal or injection well in Texas carries two recurring filings. Form H-10, the annual monitoring report, reports the well’s monthly injection pressures and volumes once a year on a cycle staggered by testing county. Form H-5 documents every mechanical integrity test. Since June 1, 2026 the test schedule arrives by monthly email instead of mail.

On this page
  1. Who files an H-10
  2. What goes on the H-10
  3. When the H-10 is due, and how it is filed
  4. When an H-10 is not filed
  5. Form H-5: documenting mechanical integrity
  6. H-5 notices now come by monthly email
  7. Running and filing an H-5 pressure test
  8. Frequently asked
  9. Official sources

Who files an H-10

Form H-10, the Annual Disposal/Injection Well Monitoring Report, must be filed for every permitted injection or disposal well, regardless of its current status, for the life of the permit. Statewide Rule 9 requires the operator to monitor injection pressure and rate at least monthly, report the results to the Commission annually, and keep the monitoring records for at least five years. A new permit for a well that has not been drilled yet still requires an annual H-10.

  • A shut-in disposal or injection well keeps filing its H-10.
  • A permitted well that is actively producing is covered by its production well status report (Form W-10 or G-10) instead.
  • A well converted to production reports for the part of the cycle up to the conversion date; its production tests satisfy the requirement from then on.

What goes on the H-10

  • The average and maximum injection pressure for each month of the reporting cycle.
  • The total volume of liquid and gas injected each month, at standard temperature and pressure. If nothing was injected during the cycle, the online form has a “no volume to report” option.
  • Optionally, unless the permit requires it, the minimum and maximum tubing-casing annulus pressure and how many readings were taken each month. Under certain conditions this can be accepted as an alternative mechanical integrity demonstration.
  • The injection interval and the tubing and packer depth.
  • Every fluid type injected during the cycle, as a whole-number percentage of the total, adding up to 100%.

Annulus monitoring only counts if it is done properly. Leaving the tubing-casing pressure observation valves open is cited as an operating violation and voids any annulus monitoring credit.

When the H-10 is due, and how it is filed

The H-10 cycle is staggered by the testing county for the field the well is completed in, the same cycle used for production well status reports, and it comes due at the same time. Each well’s due date can be looked up in the Commission’s online H-10 query under “Filing Cycles by Field.” The Commission mails courtesy letters about 3.5 months before the due date and posts the blank H-10 in its online system at the same time.

The H-10 is filed through an RRC Online account; the Commission has not accepted paper H-10s since September 1, 2022. It is not one of the forms in LoneSTAR, the newer system that now carries the P-18, P-5, W-3C and W-3X. Statewide Rule 1 requires the supporting documents used to prepare the monitoring records to be kept for the same five years as the records themselves.

When an H-10 is not filed

The Commission sends a second notice 30 days after the due date. If the operator has not contacted Technical Permitting about compliance within 30 days of that second notice, enforcement action begins: the Commission lists sealing the well where there is no production on the lease, and severing the lease pipeline connection where there is. It also states that it will work with an operator who is making a diligent effort to comply, so answering its notices matters.

A common version of this problem is inherited. If you take over a well with a delinquent H-10 and limited records from the prior operator, the Commission’s guidance is that a well shut in for a long, documentable period can report zero injection pressures and volumes. Otherwise, the oil or gas to water ratio from the well test report (Form W-10 or G-10) can be used to estimate the water volumes, with the values marked as estimated.

Form H-5: documenting mechanical integrity

All injection and disposal wells must demonstrate mechanical integrity, and the pressure test is usually the simplest and least expensive way to do it. Form H-5 documents every mechanical integrity test performed on the well: not only the scheduled or passing ones, but failed and inconclusive tests too.

  • Wells with surface casing set and cemented through the entire zone of usable-quality groundwater are tested every five years.
  • Wells without that full surface casing protection are tested more often.
  • A passing test resets the clock: the schedule runs from the most recent test, whether the Commission scheduled it or it followed a workover.
  • A failed test still gets filed. It shows the Commission the test was performed, and the Commission’s H-5 guidance gives the operator 60 days to repair and retest the well.
  • A well that has been used for injection or disposal keeps demonstrating mechanical integrity periodically until its permit is canceled, even if it is not currently being used for injection.

H-5 notices now come by monthly email

Since June 1, 2026 the Commission no longer mails H-5 notifications. They go by email, on the first working day of each month (previously the letters were quarterly), to the primary email address on your Form P-5. Each email carries a spreadsheet with three tabs:

  • Well Test and Survey Schedule: every UIC well with a test due in the next six months.
  • Delinquency Notice: every overdue H-5.
  • H-5 Violation Notice: every outstanding failed or inconclusive test. The separate paper letter for each failed or inconclusive test is no longer sent.

You do not need a LoneSTAR account to receive these emails, but you do need a primary email on your P-5. Without one, the Commission says you will not receive the notices at all. The email can be updated with an online P-5 records-only filing or the P-5 address change form. Filing the H-5 itself has not changed.

Running and filing an H-5 pressure test

  1. Give the district office 48 hours’ noticeNotify the appropriate RRC district office at least 48 hours before the test. Anyone the operator authorizes can run the standard H-5 pressure test; there is no requirement to hire a service or testing company.
  2. Set the test pressureTest to 500 psig or the maximum authorized injection pressure, whichever is less, but no less than 200 psig, and keep a 200 psig differential between the test pressure and any tubing pressure. Wells that inject down casing test at the maximum permitted pressure.
  3. Test with the right annulus fluidWells permitted to inject liquids are tested with a liquid-filled annulus unless the Commission approves otherwise. Packer fluid additives that reduce the sensitivity of the test, such as drilling mud or polymer gels, are prohibited.
  4. Record and hold the pressureMonitor the tubing-casing test pressure on a one-pen recorder, with gauges on the tubing, casing and surface casing. A successful test stabilizes within 10% of the required test pressure and holds for at least 30 minutes (60 minutes for a gas injection well tested with a gas-filled annulus).
  5. File the H-5 online within 30 daysFile Form H-5 through the RRC Online system within 30 days of any pressure test, failed or inconclusive tests included. Attach the pressure recorder chart if the test was not witnessed by the Commission. Hard-copy H-5s have not been accepted since May 1, 2021, and filing online means no duplicate copy goes to the district office. The result is emailed to the filer.

Frequently asked

When is my H-10 due?

The H-10 cycle is staggered by the testing county for the field the well is completed in, on the same cycle as production well status reports. You can look up a well’s due date in the Commission’s online H-10 query, and the Commission mails a courtesy letter about 3.5 months before it.

Do I file an H-10 for a shut-in disposal well?

Yes. An H-10 is required for every permitted injection or disposal well regardless of its current status, for the life of the permit, and a shut-in well keeps filing it.

How often does a disposal well need an H-5 pressure test?

Every five years for wells with surface casing set and cemented through the entire zone of usable-quality groundwater, and more often for wells without that protection. The schedule runs from the most recent test, and upcoming tests are listed in the Commission’s monthly H-5 email.

Why did my H-5 notices stop arriving by mail?

Since June 1, 2026 the Commission sends H-5 notices by email on the first working day of each month, to the primary email address on your Form P-5. If your P-5 has no primary email, you will not receive them, so check that it is set.

Do I have to file an H-5 for a failed test?

Yes. Form H-5 documents every mechanical integrity test, including failed and inconclusive ones. A failed test then appears on the H-5 Violation Notice tab of the monthly email, and the Commission’s guidance gives 60 days to repair and retest.

Official sources

Emergent Environmental is not affiliated with the Railroad Commission of Texas. This guide is informational; the official H-10 and H-5 instructions are authoritative.

Keep reading

Let us file it for you.

We keep each well’s H-10 cycle and test schedule, prepare the reports from your own pressure and volume records, and file them on your sign-off. Ask us for a flat monthly quote.

Contact usClose

Contact us

You hear back the same business day.

Get a quote