The two-mile area of review for Permian Basin disposal wells

- 1. Guide
- 03 of 11
- 2. Subject
- Area of review
- 3. Updated
- 4. Reading time
- 9 min
Since June 1, 2025, every new or amended saltwater disposal well application in the Permian Basin has gone through a two-mile area of review. Every well within half a mile must pass on its cementing and plugging records. Orphaned wells, or wells with missing records, between half a mile and two miles cut the permit’s maximum surface injection pressure by 0.05 psi/ft.
On this page
- What changed on June 1, 2025
- Inside half a mile: pass or fail
- Half a mile to two miles: the records check
- What goes in a Permian application
- How the pressure and volume limits are set
- Earthquakes are reviewed separately
- The rest of the application
- Where an area of review takes the most time
- We can do this for you
- Frequently asked
- Official sources
What changed on June 1, 2025
Statewide Rules 9 and 46 have long asked a disposal well applicant to review the public records of wells that penetrate the proposed disposal zone within a quarter mile. An old well that is not properly plugged can carry injected water out of the zone, so the review exists to find those wells before the new one is permitted.
In the Permian Basin that review now reaches two miles. The Commission’s May 15, 2025 notice to operators gave three reasons: large historical and current disposal volumes, rising pressure in the disposal formations, and dense historical drilling with many wellbores through active disposal zones. Since June 1, 2025, new and amended disposal applications there have been evaluated under its Permian Basin Disposal Well Review.
- Where: every county in Railroad Commission Districts 7C, 8 and 8A.
- Which applications: every Rule 9 disposal application, and every Rule 46 application marked for disposal. Waterflood, enhanced recovery, pressure maintenance and storage wells are not part of this review.
- What it decides: whether the wells around the site keep injected water confined, the maximum surface injection pressure, and the maximum daily injection volume.
Inside half a mile: pass or fail
The Commission calls the inner half mile a pass/fail radius. The applicant must assess the completion and cementing records of every known well inside it, and the offset wells must show:
- Cement across the injection interval, adequate to keep injected water in that interval.
- Every applicable plugging record, showing that the base of usable-quality groundwater is protected from the new well’s injection.
- No orphaned, improperly plugged or abandoned wells anywhere inside the half mile.
A well that cannot be shown to meet these tests fails the half-mile review. Sometimes the record exists and only needs finding: older wells often have paper or scanned files that the online queries do not return. Sometimes the drilling record shows the well never reached the disposal zone. Where no plugging record can be found at all, the Commission’s guidance allows the well to be re-entered and plugged under Statewide Rule 14.
Half a mile to two miles: the records check
The Commission calls the outer band a wellbore data integrity radius. Wells there do not decide the application on their own: the Commission says they are not necessarily cause for denial unless confinement cannot be shown. They do change the permit. If any of them are orphaned wells, or have insufficient cementing, plugging or completion records, the permit’s maximum surface injection pressure is reduced by 0.05 psi/ft.
The deduction applies to wells that are not remedied. A record that turns up, or a well shown to be properly plugged, keeps it off the permit, which is why the outer band is worth researching rather than simply listing.
What goes in a Permian application
Alongside the application form, the Commission’s checklist asks for its Excel workbook, the data behind it, a map, a cross-section, and the seal of a licensed engineer or geoscientist. The workbook is the UIC Permian Review. The Commission’s Permian Basin Disposal Well Review page posts version 1.3; the 2025 notice still links the original version 1.0. Download a fresh copy from the review page for each application.
- Well Template: the subject well’s technical data, with depths in true vertical depth and, beside each value, the page of the data appendix it comes from.
- AOR Template: every well inside two miles, sorted by distance. Wells within half a mile take the full set of columns, casing, cement and plugging included; wells out to two miles take the basic ones. Anything a record does not show is marked “unavailable” or “NA”, never estimated.
- A map of the subject well and every offset well, each numbered to match its row in the AOR Template.
- A cross-section across the whole two-mile area, showing the injection interval and the confining layers above and below it, with the reference wells it relies on.
- A data appendix: the completion and plugging records for every well within half a mile and the source data for the Well Template, collected into one PDF with a table of contents and page numbers.
- The seal of a Texas Professional Engineer or Professional Geoscientist on the engineering and geologic work, such as the stress and fracture gradient analysis and the well log interpretation.
How the pressure and volume limits are set
The workbook turns that data into the permit’s limits. The maximum surface injection pressure comes from the closure stress of the confining layers above and below the injection interval, and no gradient above 0.50 psi/ft is granted administratively. The maximum daily injection volume comes from the initial average reservoir pressure. The maximum injection rate is that daily volume divided by 1,440 minutes.
Permits issued under the review carry matching conditions: a bottomhole pressure measurement before injection begins and once a year after, a fracture gradient test before injection with a sealed report, a radial cement bond log on the long string, and daily injection volumes reported monthly to TexNet.
Earthquakes are reviewed separately
The Commission’s seismicity review runs alongside the Permian review. It looks for earthquakes of magnitude 2.0 or greater, in the USGS and TexNet catalogs, inside an area of interest around the well: 5.64 miles (9.08 km) for a shallow well and 15.53 miles (25 km) for a deep one. The line between shallow and deep is drawn differently in the Delaware and Midland basins, and the seismicity review page sets out both. For shallow Permian wells, the Permian review is what evaluates whether pressure stays confined.
The rest of the application
- The form: Form W-14 for disposal into a zone that is not productive (Rule 9), or Form H-1 with H-1A for a productive zone (Rule 46). The Commission treats a zone as productive if there is current or past production from the same interval within two miles.
- Maps: a map of every well of public record within a quarter mile, with a table of the wells that reach the top of the injection zone (lease, well number, API number, total depth, date drilled, status and date plugged), and a notice map of the wells and active drilling permits within half a mile, each labeled with its operator. Both are on the Commission’s list of application attachments, inside the Permian and out.
- Notice: a copy of the application to the surface owner, to the operator of every well or active drilling location within half a mile (permanently plugged wells excepted), and to the county clerk, plus the city clerk if the well is inside city limits.
- Publication: a notice published once in a newspaper of general circulation in the county, on or before the filing date, with a notarized affidavit and the clipping.
- Protest: affected persons and local governments have 15 days to protest, counted from the latest of the filing, the notice and the publication. If a protest is not withdrawn, the applicant can ask for a hearing.
- Timing: staff have 30 days to declare an application complete or ask for more, then 15 days to grant or deny it. The Commission reports that complete applications have averaged 23 days and incomplete ones 46.
Where an area of review takes the most time
The rules above are the Commission’s. These are the places the work itself slows down, in our experience.
- Wells with no full API number. Some old wells, often dry holes, carry only a county code in the Commission’s data. They are still wells in the circle, and each one has to be identified, not dropped.
- Stale data. The Commission updates its well layers twice a week. Pull them fresh for each review and keep the copy you used with the application.
- County lines. If the two-mile circle crosses into the next county, that county’s wells count too.
- Older records. For many older wells the completion or plugging record exists only as a scanned file, or not online at all. Finding those is most of the half-mile work.
- Depths. Completion records often give measured depth, and the workbook asks for true vertical depth. On a deviated well the two differ, so the record has to be read, not copied.
- Coordinates. The workbook and the cross-section use NAD83 latitude and longitude. Some older data sets use NAD27, and mixing the two moves a well, sometimes across the half-mile line.
We can do all of this for you.
Everything in this guide is work we do. Tell us where the well is and which zone it will inject into, and we prepare the area of review around it.

- Every well inside two miles, from the Commission’s current well data, listed by distance and numbered.
- The maps: the two-mile map numbered to match the AOR Template, the quarter-mile area of review map with its table of wells, and the half-mile notice map.
- Completion, cementing and plugging records for every well inside half a mile, with any that would fail flagged early, while there is still time to deal with it.
- Orphaned wells and missing records called out across the whole circle, since each one can cost injection pressure.
- The Commission’s AOR Template filled in, and the well records assembled and numbered for the data appendix.
Frequently asked
What is the area of review for a Texas disposal well?
Under Statewide Rules 9 and 46 the standard area of review is a quarter mile around the proposed well. In the Permian Basin (Districts 7C, 8 and 8A), new and amended disposal applications have been reviewed out to two miles since June 1, 2025, with a pass/fail test inside half a mile.
Does the two-mile review apply to amended permits?
Yes. It applies to new and amended saltwater disposal well applications in Districts 7C, 8 and 8A, including Rule 46 applications marked for disposal. Waterflood, enhanced recovery, pressure maintenance and storage wells are not part of it.
What happens if a well within half a mile has no plugging record?
It fails the half-mile review until it is resolved. The record may exist in older paper or scanned files, the drilling record may show the well never reached the disposal zone, or the well can be re-entered and plugged under Statewide Rule 14.
Do wells between half a mile and two miles stop a permit?
Not on their own. Orphaned wells, or wells with insufficient cementing, plugging or completion records, reduce the permit’s maximum surface injection pressure by 0.05 psi/ft if they are not remedied. The Commission says they are not necessarily cause for denial unless confinement cannot be shown.
What maps does a Texas disposal well application need?
A map of every well of public record within a quarter mile of the proposed well, with a table of the wells that reach the injection zone, and a notice map of the wells and active drilling permits within half a mile, labeled with their operators. In the Permian Basin the application also needs a two-mile map numbered to match the AOR Template.
Does a Permian disposal application need an engineer’s seal?
The engineering and geologic work does. The Commission asks for the seal of a Texas Professional Engineer or Professional Geoscientist on studies such as the stress and fracture gradient analysis and the well log interpretation.
Official sources
- Permian Basin Disposal Well Review (RRC)
- UIC Permian Review workbook, version 1.3 (RRC, Excel)
- Permitting disposal wells in the Permian Basin, RRC presentation, July 2025
- The original notice to operators, May 15, 2025 (RRC)
- Injection and disposal permits: technical review (RRC)
- Injection and disposal permits: application attachments (RRC)
- Injection and disposal permit applications FAQ (RRC)
- Seismicity review (RRC)
- Data sets available for download (RRC)
- Statewide Rules 9 and 46, Chapter 3 rule text (RRC)
Emergent Environmental is not affiliated with the Railroad Commission of Texas. This guide is informational; the Commission’s Permian Basin Disposal Well Review guidance and Statewide Rules 9 and 46 are authoritative.